The Meadows Donnelly, Idaho
In 2004 Granite Excavation, Inc. landed the contract to begin phase 1 of this project. Phase 1 included the installation of 5,394ft of sanitary sewer, and 5,641ft of municipal water. This installation was very difficult due to a very high water table, which required several submersible pumps. Read More... |
Aspen Crest phase 1Cascade, Idaho
Aspen Crest was a 3 month project that included 300,000yds of excavation and construction of 3 miles of 24ft wide roadway. Granite Excavation, Inc. was also responsible for clearing and grubbing, gravel hauling, gravel placement, culvert installation, and construction of 17 private driveways. |
|
Whitetail ResortMcCall, Idaho
Granite Excavation, Inc. was a subcontractor on this project for Masco, Inc. Our crews had the responsibility of installing sanitary sewer and municipal water. Fluctuating soils and extremely hard rock made our production vary from 150ft per day to 500ft per day. However, the schedule was met on time and on budget. Granite Excavation, Inc. along with Masco, Inc were awarded the contract for both the McCall junior high school construction, and also the Donnelly elementary school expansion. Work is to begin the first part of June and continue into July. |
St.Katherine Drexel ChurchCascade, Idaho
This job included stripping of 1500yds of topsoil, over-excavation of building pad and placement of structural fill. Our crews were also responsible for installing a complete drain system under the building pad. This project also included importing 2000yds of base rock and 500yds of ¾ road mix for parking area. Once the building was complete Granite Excavation, Inc. did final grading and landscaping. |
Eaglenest phases 1-2 Cascade, Idaho
This was a 2 year project that included construction of nearly 8 miles of 24 ft. wide roadway. Granite Excavation, Inc. was also responsible for wetland mitigation and culvert installation in the roadways. This project had an excavation of nearly 500,000yds of material much of which was very solid rock. We were also in charge of placing 6inches of road mix on the roadways. Doing this project also led us to numerous driveways and residential excavations in this subdivision. |
Tamarack ResortDonnelly, Idaho
Granite Excavation, Inc. crews took on the task of installing 14 grinder pumps for the Clearwater town homes at Tamarack. This job was very tricky due to the fact that house construction was taking place at the same time, and the site was very active. Much of this work had to be done with compact equipment because the locations of these pumps were very complex. Our crews also dug out house pads for the Staircase chalets, and installed sewer and water for onsite use. Granite Excavation, Inc. has also provided trucking support for Tamarack crews. |
Herrick Hills phase 1Cascade, Idaho
Herrick Hills was a six month contract that included 550,000yds of excavation and construction of 3 miles of roadway. This project was very difficult due to the steep terrain and extremely hard rock encountered. Granite Excavation, Inc. was also responsible for clearing and grubbing, culvert installation, and construction of 40 residential driveways. Granite Excavation, Inc. will also be constructing 2700ft long acceleration and deceleration lanes at the entrance to this project. This is a very complex project due to the quality control and erosion control methods that must be upheld to meet Idaho Transportation Department standards. |
Jug Mountain Ranch Lakefork, Idaho
Granite Excavation, Inc. was a subcontractor on this project and had duty to strip roads of topsoil and place material for landscaping berms. Our crews were also responsible for pond excavation and trucking support. |
Broken RidgeMcCall, Idaho
Granite Excavation, Inc. was a subcontractor on this project and our crews were responsible for clearing and grubbing, and excavation of road sub-grade. We were also responsible for importing bedding chips and reject sand to support pipe crews. |